Environment

How Do You Get an Environmental License in Ecuador? 2026 Guide

Site walk on a rehabilitated road, wearing a hard hat
In this article
  1. Who grants environmental permits today
  2. Environmental certificate, registration or license: which one applies to you
  3. How to get an environmental license in Ecuador, step by step
  4. Time limits: what the rules say and what depends on you
  5. After the license: obligations that never end
  6. Common mistakes that delay or jeopardize your license
  7. How I can help

To obtain a licencia ambiental (environmental license) in Ecuador, you register your project in the Sistema Único de Información Ambiental (SUIA, the Ministry's online permitting system), obtain the certificado de intersección (intersection certificate), submit an environmental impact study prepared by a qualified consultant, complete the citizen participation process, provide an insurance policy and pay the fees. Only then does the authority issue its resolution. This guide walks you through each step under the regulations in force in 2026, the time limits the law sets, and the mistakes that most often delay projects.

Who grants environmental permits today

Before you start, it helps to understand a recent institutional change. Under Decreto Ejecutivo 94 (Executive Decree 94) of August 14, 2025, the Ministerio del Ambiente, Agua y Transición Ecológica (MAATE, Ministry of Environment, Water and Ecological Transition) was merged by absorption into the Ministerio de Energía y Minas (Ministry of Energy and Mines), which was renamed Ministerio de Ambiente y Energía (Ministry of Environment and Energy) and took over environmental powers. The same decree provides that MAATE's plans, programs, projects, rights and obligations are taken over by the new ministry. Later acts published in the Registro Oficial (Official Gazette) reflect this.

For you as an operator, the practical upshot is this: environmental permitting (regularización ambiental) is still processed through the SUIA, and the register of environmental consultants remains in force, now under the name of the Ministerio de Ambiente y Energía. The substantive rules did not change with the merger. They are still those of the Código Orgánico del Ambiente (COA, Organic Environmental Code) and its Reglamento (RCOA, implementing regulations), the latter with amendments in 2022 (Decree 573), 2023 (Decrees 754 and 844) and 2024.

The National Environmental Authority and accredited GADs

It is not always the Ministry that issues your permit. The COA provides that provincial, metropolitan and municipal Gobiernos Autónomos Descentralizados (GAD, decentralized autonomous local governments) may carry out impact assessment, environmental control and monitoring through accreditation granted by the Autoridad Ambiental Nacional (National Environmental Authority) (art. 165). Earlier regulations referred to them as “autoridades ambientales de aplicación responsable” (responsible enforcement environmental authorities). Today they are called competent environmental authorities accredited under the Sistema Único de Manejo Ambiental (SUMA, the Single Environmental Management System). For example, the Distrito Metropolitano de Quito (Metropolitan District of Quito) and the Gobierno Provincial del Guayas (Provincial Government of Guayas) process environmental licenses through the SUIA.

That said, the Ministry retains exclusive competence in cases such as strategic-sector projects, projects within the Sistema Nacional de Áreas Protegidas (National System of Protected Areas), zonas intangibles (intangible zones, strictly protected areas) or the Patrimonio Forestal Nacional (National Forest Heritage), projects promoted by a provincial GAD, and all cases where there is no accredited authority (COA, art. 166). You do not have to guess, because the SUIA assigns the competent authority for you.

Environmental certificate, registration or license: which one applies to you

The COA classifies environmental impact as non-significant, low, medium or high, and establishes that the SUIA automatically determines the type of permit (art. 172). When you enter your activity, the system looks it up in the catálogo de actividades (catalog of activities) and defines three things: the competent environmental authority, the level of impact and the administrative authorization required (RCOA, art. 422).

ImpactAuthorizationWhat it involves
Non-significantCertificado ambiental (environmental certificate)No permit is required; you follow guides of good environmental practice (RCOA, art. 427)
LowRegistro ambiental (environmental registration)SUIA form, intersection certificate, environmental management plan and payment for administrative services. Hiring a consultant is not mandatory (RCOA, arts. 428–429)
Medium or highLicencia ambiental (environmental license)Environmental impact study, citizen participation, insurance policy and fees (RCOA, arts. 431–432)

Consider a hypothetical example. A small neighborhood car wash will probably fall into a lower category, while an asphalt plant, a quarry or a new interprovincial road usually require a license. The category is set by the catalog, not by how the operator sees things. That is why it pays to run the check in the SUIA at the very start, before you commit to schedules or budgets.

How to get an environmental license in Ecuador, step by step

These are the steps of the process for medium- and high-impact projects, according to the RCOA and the official procedure page.

1. Project registration and intersection certificate

First you create your user account in the SUIA and register the project: sector, activity, proponent details and the coordinates of the area. The system generates the certificado de intersección, which shows whether the project overlaps with the Sistema Nacional de Áreas Protegidas, the Patrimonio Forestal Nacional or zonas intangibles (COA, art. 175; RCOA, art. 423). If it overlaps with a protected area, you also need an environmental feasibility report from the area's management (RCOA, art. 424).

2. Environmental impact study (EsIA)

The estudio de impacto ambiental (EsIA, environmental impact study) is the technical core of the process. Under the Reglamento, it must be prepared by qualified environmental consultants (RCOA, art. 433) and must contain, among other things, the project description, the analysis of alternatives, the physical, biotic and socioeconomic baseline, the areas of influence, the risk analysis, the impact assessment and the environmental management plan with its sub-plans (RCOA, art. 434). I explain the management plan in detail in my guide to the Plan de Manejo Ambiental (PMA, Environmental Management Plan) in Ecuador.

Keep in mind a point that is often overlooked: the operator and whoever prepares the study are jointly and severally liable for the truthfulness and accuracy of its content (COA, art. 180). A study copied from another project, or one with weak baseline data, puts you at risk, not just the consultant.

3. Technical review and observations

The authority reviews the study, may inspect the site and notifies you of its observations. You can request a single clarification meeting to understand what is being asked of you (RCOA, art. 437). If the observations are not resolved within the review cycles provided, the review fee is charged again and, after a third failed cycle, the case is closed (RCOA, art. 439).

4. Citizen participation

Once there is a favorable technical decision, the authority orders the start of the citizen participation process (RCOA, art. 438). Its purpose is to inform the population in the area of influence and to gather opinions and observations so as to incorporate into the study those that are technically and economically feasible (COA, art. 184). The process is led by the authority with qualified environmental facilitators, and its outcome is documented in a systematization report. This chapter of the Reglamento was amended in 2023 and is subject to the ruling of the Corte Constitucional (Constitutional Court) in judgment 51-23-IN/23. That is why you should check the conditions currently applicable to your case well in advance, especially if there are communities or Indigenous peoples in the area.

5. Insurance policy or guarantee, and payment of fees

Authorizations that require an environmental impact study call for insurance or a financial guarantee covering the operator's environmental liabilities, kept in force throughout execution and until the activity ceases (COA, art. 183). Public entities and companies with at least two-thirds public capital are exempt from providing the policy. That exemption does not release them from answering for compliance with the environmental management plan (COA, art. 183).

As for fees, the Ministry's official procedure page states that reviewing and issuing a license for a new (not-yet-operating) project (ex ante) costs 1 per 1,000 of the total project cost, with a minimum of USD 1,000 for high impact and USD 500 for medium impact, under Acuerdo Ministerial 083-B (Ministerial Agreement 083-B, R.O. 387, November 4, 2015). For high-impact projects, the cost of the environmental facilitator is added. Always confirm current amounts with the competent authority, because accredited GADs may apply their own local ordinances.

6. Resolution and issuance of the license

Once the policy has been submitted and the fees paid, the authority must issue the resolution within a maximum of 15 days (RCOA, art. 442). The resolution sets out the obligations you will have to meet during all phases of the project (RCOA, art. 443), so read it carefully: it is your compliance roadmap. According to the official procedure page, the license remains in force for the useful life of the project, works or activity.

Time limits: what the rules say and what depends on you

The Reglamento sets time limits for the authority. Under Ecuadorian law, these time limits (términos) are counted in business days, that is, excluding weekends and public holidays.

StageMaximum time limit (RCOA)
Initial review of the EsIA and notification of observations30 days (art. 438)
Correction of observations by the proponent15 days, extendable once up to 30 days (art. 439)
Review of the corrections10 days (art. 438)
Overall technical decision, including corrections75 days from the start of the procedure (art. 438)
Resolution after policy and payment15 days (art. 442)

Some parts of the timeline are not set by the rules: the time it takes to prepare a good study (field surveys, sampling, laboratory analysis), the quality of the first submission and the actual duration of citizen participation. In practice, what shortens the process most is a solid study from the first version. If you manage a construction project, build the environmental permit into the master schedule from the design phase. I cover this in how to avoid delays and cost overruns in construction projects.

After the license: obligations that never end

The license is not the end of the process but the start of control and monitoring. The main obligations are:

  • Comply with the environmental management plan. Under the COA, compliance with the PMA is mandatory for the operator (art. 181), and the authority may require it to be updated at any time on reasoned technical grounds (art. 182).
  • Monitoring. You must keep monitoring records according to your plan and report them at least once a year (RCOA, art. 484).
  • Environmental management reports. Medium- and high-impact projects submit annual environmental management reports (RCOA, art. 491).
  • Environmental compliance audit. It is submitted one year after the license is granted and every three years thereafter, and it must be prepared by a qualified consultant (RCOA, arts. 492–493).
  • Key date. Environmental compliance reports (IAC), environmental management reports and environmental compliance audits are due by January 15 each year, as set out in the authorization (RCOA, art. 485). Have your policy renewed by that date as well.
  • Policy in force. Renew it on time. It must be maintained throughout operations.
  • Project changes. An expansion or modification may require a supplementary study, an update of the PMA or a new permitting process (COA, art. 176; RCOA, arts. 445–446).

Audits and inspections can result in conformities, minor or major non-conformities, and an obligation to submit an action plan (RCOA, arts. 498–505). An orderly management system, for example one based on ISO 14001, makes it much easier to arrive at every audit with the evidence ready.

On a construction project, compliance is won or lost every day in the work area, and the documentation must reflect what actually happens in the field. Worker safety goes hand in hand with it; if that side interests you, see the guide to safety on construction sites.

Common mistakes that delay or jeopardize your license

  1. Starting works before you have the resolution. If you are already operating without a permit, the Reglamento requires you to submit an environmental diagnosis and an action plan, and to bring the activity into compliance within the deadline set by the authority (art. 457), without prejudice to any administrative action that may apply.
  2. Incorrectly entered coordinates. An error in the polygon changes the result of the intersection certificate and may force you to update it during the process (RCOA, art. 425).
  3. Splitting the project to obtain a lower-category permit. This is prohibited.
  4. Generic or copied studies. They lead to observations, new review cycles and additional fees. In the worst case, the case is closed.
  5. Underestimating citizen participation. It is a stage with its own rules, and feasible observations must be incorporated into the study.
  6. Forgetting the ongoing obligations: January 15, the first-year audit and renewal of the policy.
  7. Expanding without notice. A new production line or an additional area may require a supplementary study or going through permitting again.

If your project involves mining, bear in mind that the Ley Orgánica para el Fortalecimiento de los Sectores Estratégicos de Minería y Energía (Organic Law for Strengthening the Strategic Mining and Energy Sectors; R.O. 234, Fifth Supplement, March 2, 2026) introduced changes to the authorizations required before mining activity. Review your case with specialized mining advice.

How I can help

I am an environmental engineer and qualified and registered environmental consultant, with experience in road infrastructure, asphalt plants, and environmental and mining consultancy. I help you determine which permit you need, prepare the studies and the environmental management plan, and organize ongoing compliance so that audits are never a surprise. You can see a summary of the permit types in the permit guide or write to me directly.

Frequently asked questions

How do I know whether my project needs an environmental license or just an environmental registration?

It is not the operator's decision. When you enter the activity and its location in the Sistema Único de Información Ambiental (SUIA, the Ministry's online permitting system), the system places it in the catalog of activities and determines the competent authority, the level of impact and the permit required. Under the Reglamento al Código Orgánico del Ambiente (the regulations implementing the Organic Environmental Code), low-impact activities are permitted through a registro ambiental (environmental registration) and medium- or high-impact activities with a licencia ambiental (environmental license); activities with non-significant impact receive a certificado ambiental (environmental certificate).

Can I handle the environmental license myself, without a consultant?

You can manage the account and the procedure in the SUIA yourself, but the environmental impact study required for a license must be prepared by a qualified environmental consultant, according to the Reglamento al Código Orgánico del Ambiente. By contrast, hiring an external consultant is not mandatory for either an environmental registration (low impact) or an environmental certificate (non-significant impact).

How long does it take to issue an environmental license?

The Reglamento sets maximum time limits for the authority, for example 75 days for the technical decision on the study (including observations and corrections) and 15 days to issue the resolution once the insurance policy has been submitted and the fees paid. On top of that comes the time needed to prepare the study and to complete the citizen participation process, which depend on each project. Plan with plenty of margin and do not schedule works before you have the resolution.

Does the environmental license expire?

According to the official procedure page published by MAATE (now the Ministerio de Ambiente y Energía, Ministry of Environment and Energy) on gob.ec, the environmental license remains in force for the useful life of the project, works or activity. That does not mean it is a one-off procedure: it carries ongoing obligations such as complying with the environmental management plan, submitting reports and audits, and keeping the insurance policy in force.

What changed with the merger of MAATE into the Ministry of Environment and Energy?

Decreto Ejecutivo 94 (Executive Decree 94) of August 14, 2025, ordered the merger by absorption of the Ministerio del Ambiente, Agua y Transición Ecológica (Ministry of Environment, Water and Ecological Transition) into the Ministerio de Energía y Minas (Ministry of Energy and Mines), renamed Ministerio de Ambiente y Energía, which takes over its powers. The decree provides that plans, programs, rights and obligations pass to the new ministry. In practice, procedures are still carried out in the SUIA and the register of environmental consultants is still operating, now under the name of the Ministerio de Ambiente y Energía.

What happens if I am already operating without an environmental permit?

The Reglamento al Código Orgánico del Ambiente provides that operators carrying out works or activities without authorization must submit an environmental diagnosis and, where applicable, an action plan, and that the authority sets a deadline to begin the permitting process. This does not rule out any administrative action that may apply, so it is best to act as soon as possible and with professional advice.

Who issues the license: the Ministry or the municipality?

It depends. The Código Orgánico del Ambiente reserves certain cases for the Autoridad Ambiental Nacional (National Environmental Authority), for example strategic sectors, protected areas and national forest heritage, or places where there is no accredited authority. In other cases, an accredited provincial, metropolitan or municipal GAD (local government) may be competent, such as the Distrito Metropolitano de Quito (Metropolitan District of Quito) or the Gobierno Provincial del Guayas (Provincial Government of Guayas). The SUIA tells you which authority is competent for your project.

Official sources

  1. Código Orgánico del Ambiente (Organic Environmental Code), Registro Oficial Suplemento 983, April 12, 2017 · Gobierno del Ecuador (gob.ec)
  2. Reglamento al Código Orgánico del Ambiente (regulations implementing the Organic Environmental Code), Decreto Ejecutivo 752 (text with amendments up to R.O. 347, April 16, 2024) · Gobierno del Ecuador (gob.ec)
  3. Emisión de licencia ambiental para proyectos, obras o actividades de mediano o alto impacto (official procedure page: issuing environmental licenses for medium- or high-impact projects, works or activities) · MAATE (now the Ministerio de Ambiente y Energía), gob.ec
  4. Emisión de certificado de renovación como consultores ambientales individuales (renewal certificate for individual environmental consultants, MAE-041-01-02) · MAATE (now the Ministerio de Ambiente y Energía), gob.ec
  5. Registro Oficial Suplemento 149 (Official Gazette Supplement 149), October 22, 2025 (Acuerdo MAE-MAE-2025-0035-AM, citing Executive Decrees 60, 94 and 138) · Registro Oficial / Corte Constitucional del Ecuador
  6. Emisión de licencia ambiental para proyectos de mediano y alto impacto en el DMQ (environmental licenses for medium- and high-impact projects in the Metropolitan District of Quito) · GAD del Distrito Metropolitano de Quito, gob.ec
  7. Solicitud de licencia ambiental (environmental license application) · GAD Provincial del Guayas, gob.ec
  8. Ley Orgánica para el Fortalecimiento de los Sectores Estratégicos de Minería y Energía (Organic Law for Strengthening the Strategic Mining and Energy Sectors; R.O. 234, 5th Supplement, March 2, 2026) · Asamblea Nacional del Ecuador

This article is for information only and reflects the regulations reviewed as of the update date. It does not replace a review of your specific case or the official text of each regulation. Official Spanish names are kept so you can use them with the authorities; the Spanish version is the reference text.

María Cecilia Mora Barzola

María Cecilia Mora Barzola

Environmental Engineer · Environmental and OHS consultant

Environmental engineer with more than 8 years of experience in road construction, asphalt plants, mining and industry. Master's in Project Management, International Master's in Building Technology, Rehabilitation and Management, certified ISO 9001, 14001 and 45001 internal auditor, a diploma in occupational health and safety, and a qualified and registered environmental consultant with MAATE (Ministry of Environment, Water and Ecological Transition), registration no. MAE-SUIA-0798-CI. See qualifications and experience · LinkedIn