Environment

Environmental Management Plan (PMA) in Ecuador: What It Is and When You Need One

María Cecilia Mora next to animal-crossing signage on a road project
In this article
  1. What is an environmental management plan?
  2. When do you need an environmental management plan in Ecuador?
  3. The PMA sub-plans under the Regulations
  4. How each measure should be written
  5. Practical examples of measures
  6. How PMA compliance is reported
  7. When and how to update the PMA
  8. What happens if you do not comply with the environmental management plan
  9. Common mistakes in PMAs

The plan de manejo ambiental (PMA, environmental management plan) is the document that sets out, measure by measure, how your company or project will prevent, control and correct its environmental impacts, and in Ecuador it is legally binding once approved. You need one if your activity requires a registro ambiental (environmental registration, for low impact) or a licencia ambiental (environmental license, for medium or high impact); if you only obtain a certificado ambiental (environmental certificate), you follow good-practice guides instead. In this guide I explain what it must contain, how compliance is reported and which mistakes to avoid.

What is an environmental management plan?

The Código Orgánico del Ambiente (COA, Organic Environmental Code) defines the environmental management plan as the instrument the operator is legally bound to comply with, made up of several sub-plans depending on the characteristics of the project, works or activity (art. 181 of the COA). Its purpose is to set out, in detail and in chronological order, the actions to prevent, avoid, control, mitigate, correct, offset, restore and remediate impacts.

The most important part for a manager is the second half of that article: the PMA must contain programs, budgets, the people responsible for implementation, means of verification and a schedule (art. 181 of the COA). It is not a document you write just to get through a procedure, but a work plan with money, owners and dates, against which the authority will assess you for the entire life of the project.

The technical detail is in the Reglamento al Código Orgánico del Ambiente (RCOA, regulations implementing the Organic Environmental Code), issued by Decreto Ejecutivo 752 (Executive Decree 752, Registro Oficial Suplemento 507, June 12, 2019), which remains in force with later amendments, including Decreto Ejecutivo 573 of 2022.

Who is the environmental authority today?

If you obtained your permit through MAATE, keep the institutional change in mind: under Decreto Ejecutivo 94 of August 2025, the Ministerio del Ambiente, Agua y Transición Ecológica (Ministry of Environment, Water and Ecological Transition) was absorbed by the Ministerio de Energía y Minas (Ministry of Energy and Mines), which was renamed Ministerio de Ambiente y Energía (Ministry of Environment and Energy). Its official website is ambienteyenergia.gob.ec. Permitting (regularización) is still done online through the Sistema Único de Información Ambiental (SUIA, the Ministry's online permitting system), and the authority reviewing your case may be the Ministry or a gobierno autónomo descentralizado (decentralized autonomous government, GAD) accredited under the Sistema Único de Manejo Ambiental (Single Environmental Management System) (arts. 414 et seq. of the RCOA), as is the case in several municipalities and provincial governments.

When do you need an environmental management plan in Ecuador?

It depends on the impact level of your activity. The COA classifies impact as non-significant, low, medium or high, and the SUIA automatically determines the type of permit (art. 172 of the COA). From there, the PMA requirement changes as follows:

ImpactAuthorizationPMA required?Main follow-up
Non-significantCertificado ambiental (environmental certificate)No. There is no obligation to go through permitting; the environmental good-practice guides apply (art. 178 of the COA; art. 427 of the RCOA)Sector good practices
LowRegistro ambiental (environmental registration)Yes. An environmental management plan specific to the activity (art. 178 of the COA)Informe ambiental de cumplimiento (environmental compliance report) (arts. 488 and 489 of the RCOA)
Medium and highLicencia ambiental (environmental license)Yes. It forms part of the environmental impact study, with its sub-plans (art. 434(i) of the RCOA)Informes de gestión ambiental (environmental management reports) and auditoría ambiental de cumplimiento (environmental compliance audit) (arts. 491 and 493 of the RCOA)

Two practical differences between a registro and a licencia: for a registro ambiental, hiring a qualified consultant is not mandatory (art. 428 of the RCOA), whereas the environmental impact study for a licencia must be prepared by qualified environmental consultants (art. 433 of the RCOA, as amended by Decree 573). In addition, authorizations that require an environmental impact study also require an insurance policy or guarantee covering environmental liabilities (art. 183 of the COA). If you do not have a permit yet, start with the guide on how to obtain an environmental license in Ecuador or see my environmental permits service.

The PMA sub-plans under the Regulations

Article 435 of the RCOA establishes that, depending on the nature of the project and taking into account the environmental aspects, impacts and risks identified, the PMA will contain these sub-plans:

  1. Impact prevention and mitigation plan: the core of the PMA, with the measures for each identified impact (dust, effluents, noise, water and energy use).
  2. Contingency plan: what to do in the event of spills, fires or leaks, who responds and with what resources.
  3. Training plan: staff training on the measures in the PMA itself, not generic talks.
  4. Waste management plan: sorting, storage, handover to waste managers and records for common, special and hazardous waste.
  5. Community relations plan: communication with neighbors and communities, complaint handling and social commitments.
  6. Rehabilitation plan for affected areas: how disturbed areas are restored.
  7. Wildlife rescue plan, where applicable.
  8. Closure and abandonment plan: how the site is dismantled and handed back when the activity ends.
  9. Monitoring and follow-up plan: what is measured, where, how often and how it is reported.

Note that the official list does not include an occupational health and safety (OHS) sub-plan, even though one appears in many outdated templates circulating online. Workplace safety has its own legal framework (I explain it in Occupational Health and Safety in Ecuador), although in practice the two systems need to work together, especially on contingencies and training. In addition, the detailed formats and content of the PMA are defined in the technical standard issued by the Autoridad Ambiental Nacional (National Environmental Authority) (art. 435 of the RCOA), so it is always worth checking the current terms of reference in the SUIA.

A practical lesson on the waste sub-plan: everything starts with a good baseline assessment. In the assessment of integrated municipal solid waste management that I carried out in Limoncocha, the starting point was understanding what waste is generated and how it is managed; without that foundation, any measure in a PMA is written on assumptions.

How each measure should be written

A useful PMA (and one you can defend during an inspection) presents every measure with the same structure. For example, the Municipality of Quito requires PMA updates in a matrix showing the environmental aspect, impact, proposed measure, indicator, means of verification and frequency, together with a costed schedule (see the procedure on gob.ec). Although the exact format depends on the authority, always think in terms of these columns:

  • Measure: a concrete action ("install a grease trap before the discharge point"), not an intention ("effluents will be controlled").
  • Indicator: something measurable ("maintenance tasks completed / scheduled").
  • Means of verification: records, dated photographs, invoices, waste handover certificates, laboratory reports.
  • Owner, frequency and budget: a real job title, a schedule and what it actually costs to comply.

Practical examples of measures

The following examples are hypothetical and are meant to illustrate the level of detail expected. The actual category of each activity is determined by the SUIA.

Small business: a car wash

Suppose a car wash that the SUIA categorizes as low impact and that obtains a registro ambiental. Its PMA could include:

Sub-planExample measureEvidence
Prevention and mitigationSettling tank and grease trap before the discharge point; periodic cleaningMaintenance log with dated photos
Waste managementStore sludge, oils and contaminated containers in a covered, clearly marked area, and hand them over to an authorized environmental waste manager (gestor ambiental autorizado)Handover certificates or manifests
ContingenciesSpill kit and fire extinguisher next to the chemical storage areaMonthly kit inventory
TrainingInduction for new staff on using the kit and sorting wasteSigned attendance record
Monitoring and follow-upLaboratory analysis of the discharge, at the frequency set in the PMALaboratory reports

In a case like this you also need to check whether the company requires a specific authorization for the hazardous waste it generates: not having one when it is mandatory is a serious infraction (art. 317(15) of the COA).

Treatment measures do not always have to be expensive or mechanical. I worked on the design and on-site construction of a biological wastewater treatment plant using water hyacinth (lechuguines), an example of how a nature-based solution can form part of the prevention and mitigation sub-plan when the project allows it.

Construction project: a residential building

For a construction project, the PMA must accompany every phase (earthworks, structure, finishes, closure). Typical measures:

  • Dust: wetting internal roads and stockpiles; dump trucks covered with tarps.
  • Noise: working hours in line with the municipal ordinance and machinery maintenance.
  • Debris: transport only to authorized debris disposal sites. Disposing of debris or waste at unauthorized sites is classified as a major non-conformity (art. 501(j) of the RCOA).
  • Oils and fuels: storage with secondary containment berms and handover of hazardous waste to authorized waste managers.
  • Community relations: advance notice to neighbors about noisy work and a channel for receiving complaints, with a record of responses.
  • Closure and abandonment: removal of site camps, cleanup and restoration of the area at the end.

On a construction site, the PMA is carried out in the same work area where safety is managed, so it makes sense to integrate it with the safety plan (see Construction Site Safety in Ecuador) and with the project schedule.

How PMA compliance is reported

Getting the PMA approved is only the beginning. After that, you must periodically show that you are complying with it. Under the RCOA:

PermitDocumentFrequency
Registro ambientalInforme ambiental de cumplimiento (IAC, environmental compliance report)One year after the registration is granted and every two years after that (art. 489 of the RCOA); it is due by January 15 each year
Licencia ambientalInforme de gestión ambiental (environmental management report)Annual, with the information supporting compliance with the PMA and the monitoring plan (art. 491 of the RCOA)
Licencia ambientalAuditoría ambiental de cumplimiento (environmental compliance audit)One year after the license is granted and every three years after that; the authority may shorten the interval based on the operator's performance (art. 493 of the RCOA)

Two details that are often overlooked:

  • Submission date: since the Decree 573 reform (2022), monitoring results are submitted consolidated within the environmental management reports, and the environmental management reports, environmental compliance reports and environmental compliance audits are due by January 15 each year, in accordance with the administrative authorization (art. 485 of the RCOA). Check what your own resolution establishes.
  • Who prepares the audit: environmental audits must be prepared by a qualified consultant (art. 492 of the RCOA).

In addition to these reports, the authority may carry out inspections at any time. Findings are classified as conformities, minor non-conformities, major non-conformities or observations (arts. 498 to 503 of the RCOA), and where there is non-compliance with the PMA, the operator must submit an action plan within a maximum of 15 business days from notification (art. 505 of the RCOA), setting out the findings, corrective measures, a schedule with owners and costs, indicators and means of verification (art. 506 of the RCOA). If an emergency occurs that the PMA did not anticipate, the operator must submit an emergency plan within two business days (art. 507 of the RCOA), and failing to inform the authority within 24 hours of emergencies, accidents or incidents that cause or may cause environmental damage is a serious infraction (art. 317(14) of the COA).

When and how to update the PMA

There are four situations in which the PMA must be reviewed:

  1. At the authority's request: the Autoridad Ambiental Competente (competent environmental authority) may at any time, for justified technical reasons, require modifications and updates to the approved PMA, which are subject to its approval (art. 182 of the COA; art. 496 of the RCOA).
  2. In the environmental compliance report: the IAC may include an update of the environmental management plan (art. 488 of the RCOA). It is a good opportunity to correct measures that did not work.
  3. When the activity changes: with a registro ambiental, complementary activities are processed as an update of the registration in the SUIA, attaching the project form (ficha) and the PMA, provided they do not require a licencia ambiental (art. 430 of the RCOA). However, if the modification constitutes a new project, generates medium or high impacts not covered by the permit, or expands the approved area or is located in a different sector, you must go through permitting again (art. 176 of the COA).
  4. At closure: before carrying out closure and abandonment, you submit an update of the approved closure plan, and closure cannot begin without the authority's approval (art. 508 of the RCOA).

What happens if you do not comply with the environmental management plan

The COA classifies administrative environmental infractions as minor, serious and very serious (art. 314 of the COA). Those most closely related to the PMA are:

  • Minor: failing to meet obligations under the authorization or the PMA where these are not classified as serious or very serious, and failing to submit environmental audits and monitoring reports (art. 316(2) and (3) of the COA).
  • Serious: failing to comply with the PMA without applying the corrective measures ordered by the authority, an infraction for which the COA provides for revocation of the authorization as a penalty (art. 317(16) and art. 320(5) of the COA); also obstructing the authority's control and follow-up (art. 317(21)).
  • Very serious: submitting incorrect or false information to obtain the authorization or in the control mechanisms (art. 318(5)), exceeding the permissible limits for effluents, discharges and emissions (art. 318(11)) and abandoning infrastructure or closing activities without approval (art. 318(13)).

Administrative penalties include fines, confiscation, destruction of property, temporary suspension of the activity, revocation of the authorization, loss of incentives and dismantling of infrastructure, in addition to full remediation where environmental damage has occurred (art. 320 of the COA). The amount of the fine is weighted according to the offender's economic capacity and other variables defined in the Code itself (arts. 322 to 326 of the COA), so there is no single figure. And a key point when hiring: the operator and whoever prepares the study, the PMA or the audit are jointly and severally liable for the accuracy and correctness of its content (art. 180 of the COA).

Common mistakes in PMAs

  • Copying and pasting a PMA from another project. This is the most frequent mistake. Measures that do not match your process, another company's name or equipment you do not have are spotted at the first inspection, and you are responsible for what the document says.
  • Unrealistic budgets. Entering token amounts so the plan "looks cheap" leaves measures unfunded. If laboratory monitoring costs money, it has to be in the budget.
  • Not keeping evidence. For audit purposes, a measure without a record, photo, invoice or certificate is a measure that was not carried out.
  • Forgetting reporting deadlines or not updating the PMA when processes, equipment or location change.
  • Using outdated templates with references that no longer match the COA and its Regulations.

Frequently asked questions

Does every company in Ecuador need an environmental management plan?

No. Activities with non-significant impact receive a certificado ambiental (environmental certificate), are not required to go through regularización (environmental permitting) and must follow the environmental good-practice guides. Low-impact activities (registro ambiental, environmental registration) require a specific environmental management plan, and medium- and high-impact activities (licencia ambiental, environmental license) include it within the environmental impact study. The SUIA, the Ministry's online permitting system, determines the type of permit based on your activity.

Can I prepare the environmental management plan without a consultant?

For a registro ambiental, the Reglamento al Código Orgánico del Ambiente (regulations implementing the Organic Environmental Code) states that hiring a qualified consultant is not mandatory. For a licencia ambiental, the environmental impact study (which contains the PMA) and the environmental audits must be prepared by qualified consultants. In every case, the Código Orgánico del Ambiente (Organic Environmental Code) establishes that the operator and whoever prepares the study, plan or audit are jointly and severally liable for the accuracy of its content.

How often do I have to report compliance with the PMA?

Under the Reglamento al COA, with a registro ambiental you submit an informe ambiental de cumplimiento (environmental compliance report) one year after the permit is granted and every two years after that. With a licencia ambiental you submit annual informes de gestión ambiental (environmental management reports) and an auditoría ambiental de cumplimiento (environmental compliance audit) one year after the license is granted and every three years after that. The 2022 reform set January 15 of each year as the submission date for these documents, in accordance with your authorization. Always check what your own resolution says.

What happens if I expand or change my activity?

It depends on the change. The Código Orgánico del Ambiente requires you to go through permitting again if the modification constitutes a new project, generates medium or high impacts not covered by the permit, or expands the approved area or is located in a different sector. With a registro ambiental, complementary activities are handled by updating the registration in the SUIA, attaching the project form (ficha) and the environmental management plan, provided they do not require a licencia ambiental.

Does the environmental management plan include occupational health and safety?

The list of sub-plans in article 435 of the Reglamento al COA does not include an occupational health and safety (OHS) sub-plan; those obligations are governed by labor and occupational risk regulations. Even so, the PMA should be coordinated with your safety system, especially for contingencies and training.

What happens if the authority finds non-compliance with my PMA?

Findings are classified as minor or major non-conformities, and the operator must submit an action plan within a maximum of 15 business days from notification. In addition, the Código Orgánico del Ambiente defines minor, serious and very serious infractions: failing to comply with the PMA can be a minor infraction, it becomes serious if the ordered corrective measures are not applied, and submitting false information is very serious. Penalties range from a fine to suspension of the activity or revocation of the permit.

Who handles the process after the MAATE merger?

In 2025 the Ministerio del Ambiente, Agua y Transición Ecológica (MAATE, Ministry of Environment, Water and Ecological Transition) was absorbed by the Ministerio de Energía y Minas (Ministry of Energy and Mines), which was renamed Ministerio de Ambiente y Energía (Ministry of Environment and Energy). Permitting is still handled through the SUIA before the Autoridad Ambiental Competente (competent environmental authority), which may be the Ministry or an accredited decentralized autonomous government (GAD), depending on the case.

Official sources

  1. Código Orgánico del Ambiente (Organic Environmental Code), Registro Oficial Suplemento 983, April 12, 2017 · Asamblea Nacional / Registro Oficial (copia en FAOLEX)
  2. Reglamento al Código Orgánico del Ambiente (regulations implementing the Organic Environmental Code), Decreto Ejecutivo 752 (text with amendments up to R.O. 347, April 16, 2024) · Presidencia de la República / Registro Oficial (copia en FAOLEX)
  3. Decreto Ejecutivo 573, Reforma al Reglamento al Código Orgánico del Ambiente (Executive Decree 573, amendment to the Regulations), R.O. 3S 171, October 18, 2022 · Presidencia de la República / Registro Oficial (copia en FAOLEX)
  4. Ministerio de Ambiente y Energía (Ministry of Environment and Energy), official website · Ministerio de Ambiente y Energía
  5. Sistema Único de Información Ambiental (SUIA, online environmental permitting system) · Autoridad Ambiental Nacional
  6. Pronunciamiento al seguimiento del Plan de Manejo Ambiental e Informe Ambiental de Cumplimiento (procedure for review of PMA follow-up and compliance report) · GAD del Distrito Metropolitano de Quito, gob.ec
  7. Registro Oficial del Ecuador (Official Gazette) · Registro Oficial

This article is for information only and reflects the regulations reviewed as of the update date. It does not replace a review of your specific case or the official text of each regulation. Official Spanish names are kept so you can use them with the authorities; the Spanish version is the reference text.

María Cecilia Mora Barzola

María Cecilia Mora Barzola

Environmental Engineer · Environmental and OHS consultant

Environmental engineer with more than 8 years of experience in road construction, asphalt plants, mining and industry. Master's in Project Management, International Master's in Building Technology, Rehabilitation and Management, certified ISO 9001, 14001 and 45001 internal auditor, a diploma in occupational health and safety, and a qualified and registered environmental consultant with MAATE (Ministry of Environment, Water and Ecological Transition), registration no. MAE-SUIA-0798-CI. See qualifications and experience · LinkedIn